Atherton spent $145K to delay train electrification. The rest of us paid $400M
• Atherton sued to delay Caltrain electrification in 2015 over overhead wires and tree removal concerns. • The lawsuit delayed $1.5 billion project, increasing costs to $1.9 billion and adding $400 million overall. • Federal funding of $647 million stalled from 2016 to 2017 due to legal uncertainty and political issues. • Atherton spent ~$145,000 on the lawsuit but gained no concessions; project delayed 3 years. • In 2024 California passed AB 2503 exempting rail electrification from CEQA review to prevent such delays.#Caltrain #InfrastructureDelay #CEQARead more | Comments | @hackernws